Written Notice is Mandatory; Actual Notice is Not Enough
Washington’s Supreme Court has stated on several occasions that if a notice of protest provision requires written notice, then such notice is mandatory and actual notice will not suffice. In other words, even if the owner had actual knowledge of the change, any claim for additional compensation is waived unless the contractor strictly complied with the written notice requirements. In a 2018 case, Nova Contracting v. City of Olympia, the contractor argued that it was not required to file a written protest after each rejected batch of submittals because it filed a claim for breach of the covenant of good faith and fair dealing based on the rejections, thereby giving the City actual notice of its protest. The Court disagreed, stating that because the claim is based entirely on the City’s allegedly improper rejection of its submittals, and Nova did not file a written protest immediately, it waived any claims for protested work.
The Nova decision follows other cases in which this state’s highest court has required strict compliance with notice of disputes provisions. In Mike M. Johnson, Inc. v. County of Spokane, the Court rejected an “actual notice” exception and held that the contractor’s claims for equitable adjustment due to design changes mid-performance were barred because contractual notice had not been given. In American Safety Cas. Ins. Co. v. City of Olympia, the Court ruled that a public works contractor waived its claims for increased compensation by not timely following the contract’s disputes process.
"Washington’s Supreme Court has stated that if a notice of protest provision in a construction contract requires written notice, then such notice is mandatory and actual notice will not suffice."
Requirement Not Limited by Implied Covenant of Good Faith and Fair Dealing
The contractor in the Nova case argued that the notice of protest provision did not apply to its claim for breach of the covenant of good faith and fair dealing because such a claim sounds in equity. However, the court rejected the premise of this argument, stating that breach of the covenant sounds in contract, not equity. The court reiterated that the contractor, by failing to comply with provision, waived “any claims for protested Work,” including a claim that the City’s improper rejection of its submittals violated the implied covenant. In addition, the Court in Nova held that the written notice requirement also applies to claims for expectancy and consequential damages.
Waiver of the Notice of Protest Provision by the Municipality is Possible
Washington courts have stated that if the party in whose favor the provision acts waives the protection, the notice requirement may not be enforced. That said, unequivocal evidence of an intent to waive must be shown, and this is a tough standard to satisfy. In the American Safety case, the Supreme Court held that an owner’s agreeing to enter into negotiations, without more, does not constitute an implied waiver of contractual rights.
Quantum Meruit Recovery is Still Available for Work Outside the Contract
The Court of Appeals has held, in General Construction Company v. Public Utility District No. 2 of Grant County, that for work outside of the contract, quantum meruit (as much as deserved) applies and entitles the contractor to compensation. Relying on the Supreme Court’s decision in Bignold v. King County, the Court of Appeals stated that this is a supplemental means of recovery when the contract is not applicable. But what work qualifies as being “outside” the contract remains a contentious issue. Contractors should not assume that a court will agree that the work for which they claim additional money or time is extra-contractual.
The Takeaway: Give Immediate Written Notice of any Potential Claims
Unless and until the state legislature steps in, Washington contractors are bound by the strict compliance standard. Although the Mike M. Johnson case contains a lengthy dissent (calling it unjust and out of step with Washington law to deny a contractor fair compensation where the owner had actual notice but the contractor did not also comply with “highly technical claims procedures”), and some commentators have advocated for a prejudicial standard instead (which would make it consistent with federal law), there is no sign of a change in the Washington courts.
How I Can Help
Lee Lewis is the founding member of HLL Law, which represents a select group of commercial contractors, design professionals, and public owners looking for elite, specialized construction industry legal and business guidance. If you are interested in exploring possible representation for your business, please
join our waitlist.